Construction Updates

Hillhaven
The Reserve Residences
One Holland Village

Hillhaven

Progress Status
Foundation Works
In Progress The Purchaser shall pay 10% of the Purchase Price according to the Payment Schedule.
Reinforced Concrete Works
Upcoming The Purchaser shall pay 10% of the Purchase Price according to the Payment Schedule.
Brickwalls / Partition Walls
Upcoming The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
Ceiling (Inclusive of False Ceiling)
Upcoming The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
Door & Window Frames, Internal Plastering & Plumbing
Upcoming The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
Carpark, Roads and Drains Serving The Housing Project
Upcoming The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
T.O.P. Estimated Q3 2027
Upcoming The Purchaser shall pay 25% of the Purchase Price according to the Payment Schedule.

The Reserve Residences

Progress Status
Foundation Works
In Progress The Purchaser shall pay 10% of the Purchase Price according to the Payment Schedule.
Reinforced Concrete Works
Upcoming The Purchaser shall pay 10% of the Purchase Price according to the Payment Schedule.
Brickwalls / Partition Walls
Upcoming The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
Ceiling (Inclusive of False Ceiling)
Upcoming The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
Door & Window Frames, Internal Plastering & Plumbing
Upcoming The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
Carpark, Roads and Drains Serving The Housing Project
Upcoming The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
T.O.P. Estimated Q1 2028
Upcoming The Purchaser shall pay 25% of the Purchase Price according to the Payment Schedule .

One Holland Village

Progress Status
Foundation Works
Completed The Purchaser shall pay 10% of the Purchase Price according to the Payment Schedule.
Reinforced Concrete Works
Completed The Purchaser shall pay 10% of the Purchase Price according to the Payment Schedule.
Brickwalls / Partition Walls
Completed The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
Ceiling (Inclusive of False Ceiling)
Completed The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
Door & Window Frames, Internal Plastering & Plumbing
Completed The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
Carpark, Roads and Drains Serving The Housing Project
Completed The Purchaser shall pay 5% of the Purchase Price according to the Payment Schedule.
T.O.P. Obtained
Residences and Serviced Residences (Zone 1): 24 Jul 2024
Offices and Retail (Zone 2): 5 Sep 2023
T.O.P. Obtained The Purchaser shall pay 25% of the Purchase Price according to the Payment Schedule.

*T.O.P date stated here is indicative only and is given based on estimate and information available. T.O.P date may vary over time depending on individual site conditions and situations. Information accurate as of 2 Aug 2024.